Section 1 - Notice Inviting Tender (NIT)

Name of work: 'Supply, Installation, Testing and Commissioning of LED/Solar Street Lights at [Location].' Estimated cost: ₹[X]. Tender fee: ₹[500–2,000 depending on project value]. Earnest money deposit (EMD): 2% of estimated cost. Bid validity: 90 days from submission date. Completion period: [typically 30–60 days from work order]. Eligibility: firms/companies with minimum 3 years in LED/solar lighting supply and installation; annual turnover ≥ 1.5× estimated cost; BIS-certified products only; ISO 9001 factory certification. Tender document available at [office address] from [date].

Section 2 - Technical Specification

LED Luminaire: BIS certified IS 16905 (licence number to be submitted). Wattage: [specify]. Luminous efficacy: minimum 130 lm/W. Colour temperature: [specify 4000K/5000K/6500K]. CRI: minimum Ra 70. Power factor: minimum 0.95. THD: maximum 10%. IP rating: IP65 minimum. IK rating: IK08 minimum. Housing: die-cast aluminium ADC-12. Cover: tempered safety glass minimum 4mm. Driver brand: from internationally recognised brand (Meanwell/Inventronics/Osram or equivalent - to be declared). Surge protection: 4kV/2kA per IEC 61000-4-5. Operating temperature: -10°C to +55°C. Pole: [height] GI hot-dip galvanised IS 2629, [wall thickness] mm, anchor bolt foundation. Warranty: 2 years comprehensive from manufacturer.

Section 3 - Bill of Quantities (BOQ)

Item 1: Supply of [wattage]W LED street light luminaire - [quantity] Nos. Rate per unit: ₹___. Amount: ₹___. Item 2: Supply of [height]m GI pole with anchor bolts - [quantity] Nos. Rate: ₹___. Item 3: Civil work for pole foundation (M15 concrete, excavation, backfill) - [quantity] Nos. Rate: ₹___. Item 4: Erection of pole and installation of luminaire including all fasteners and hardware - [quantity] Nos. Rate: ₹___. Item 5: Earthing per pole (GI pipe electrode, earth wire, earth pit) - [quantity] Nos. Rate: ₹___. Item 6: Testing and commissioning including lux measurement - Lump sum. Total: ₹___. GST @ 18% on supply items, @ 12% on civil and installation: ₹___. Grand Total: ₹___.

Section 4 - Special Conditions and Penalty

Quality assurance: all materials to be inspected and approved before installation. BIS marks to be verified physically on each unit. Random sample testing: minimum 5% of supply batch to be tested by a NABL lab at contractor's cost if quality is disputed. Warranty register: contractor to maintain a warranty register with each unit's serial number, installation date, and location. Warranty response: any warranted defect to be rectified within 14 calendar days of written complaint; penalty of 0.5% of defective unit value per additional week of delay. Performance guarantee: 5% of contract value as performance bank guarantee, valid for warranty period + 3 months. Defect liability period: 12 months from commissioning (separate from warranty). Liquidated damages for delay: 0.5% of contract value per week of delay, maximum 10%.